Electricity in Kazashko: maintenance and power quality measurement
After maintenance on the transformer substations and branch trimming, a week-long measurement showed that the power supply meets the standards.
KAZASHKO · 19 March 2026 · retold here on 27 September 2026
Following reports from the mayor's office in 2025, the energy company carried out maintenance on the village's two pole-mounted transformer substations. Branches around the power lines were trimmed so that there would be fewer outages in strong winds.
From 11 to 18 February 2026, a device recording the quality of the power supply was installed in one of the distribution boards. No interruptions were recorded during that period, and the company confirmed that the electricity supply in the village meets the regulatory requirements and there is no voltage drop.
This item is retold in English from an announcement by the Kazashko mayor's office.